Ruskin Dam Safety Right Abutment Upgrade Stage 1
|
Owner: BC Hydro
Prime Contractor: Matcon Excavation & Shoring
- Exploratory drilling/installation of piezometers
- Clearing, grubbing and excavation/offsite disposal of approx. 60,000m3 from mountainside and Dam abutment
- Sediment control & treatment of groundwater & surface water
- Environmental protection to Stave River & Hayward Lake reservoir
- Dewatering/wellpoints
- Bioengineering/landscaping to upper slope
- Demolition/removal of existing log flume overhanging from Dam to Powerhouse bridge
- Permanent shotcrete retaining wall c/w tie-back anchors & lock block retaining walls
- Sheet piling
- Supply/placement of blanket fill to Dam Abutment c/w HDPE drainage piping
- Roadwork construction, watermain & storm sewer
- Supply/Installation of a 2100mm dia. Multi-Plate round structure to Dam abutment
- Construction of concrete Weir House c/w mechanical/electrical & miscellaneous metals to Dam abutment
Photo Album (under construction)
View all projects
|

View full size image:
|
|
|
|
|
Project Location:
Ruskin Dam - Mission, BC
Completion Date: May 2010
Contractual Amount: $ 4,700,000
Final Amount: $ 7,000,000
|
|
|
|