Excavation & Shoring, Jet Grouting
Owner: Millenium False Creek
General Contractor: MetroCan Contractor
Excavation: 240,000 m³
Shoring :
- Shotcrete: 20,000 ft²
- 55,000 ft of hollow core bar
Jet Grouting (2 groups):
Columns: 1,100
Jet Grouting: 10,000 m (approx)
Grout Mix Jet-Grouted: litres 5,000,000(approx)
Photo Album 1
Photo Album 2
View all projects:
|

View full size image: |
|
|
|
Project Location:
False Creek - 1st and Manitoba/Quebec/Columbia
Completion Date: Job in progress. Estimated
October 2007
The Challenge:
One of the biggest excavation & shoring project in BC. The biggest Jet-Grouting job in BC. Schedule. Technical problems due to the proximity of False Creek.
|
|
|
|